A training room that felt stuffy. We measured it, traced the cause to how the room had been walled in, set out a step-by-step plan, and raised the airflow at the front by 27% before a week-long event.

Illustration, not a drawing of the site

The brief

Users said a 48-seat training room felt stuffy, worst at the front. The tenant needed it fixed, and had an event in the room the following month.

What we found

  • Supply air at the vents was 11 to 14°C and humidity about 55%: the air was cold enough and not too damp. There was simply not enough of it reaching the front.
  • The room had been part of an open floor. When partition walls enclosed it, the air balance was never reset for the new room, and two vents had been added that are not on the design drawing.
  • An airflow hood test of 24 points against the as-built drawing put the front of the room at 1,004 cubic metres an hour against a design of 1,805, 44% short. The back, on a different duct, tested at 107%.
  • The motorised dampers and the transfer air duct were already fully open, so the return path was not the problem. A volume damper shown on the drawing had never been installed.
  • Nothing in the tenant's installation could add air to the branch: the shortfall began at the building's air handling unit.

What we recommended

We gave the tenant a seven-step plan, each step followed by a few days' monitoring, and a one-page summary for the building's facility manager. After the hood test we narrowed it to what the tenant could do now: close the vents on the same duct that were costing the room most, set the room's thermal diffusers to their coldest, and ask the building to raise the air handling unit's output for a full fix.

The work

  • Site investigation, supply air temperature and humidity check, and a written findings report with a phased plan
  • Study of the as-built ACMV drawing against what is installed on site
  • Airflow hood test of 24 supply points across both branches
  • Three diffusers closed, reversibly: one relocated into the room and two on the same duct outside it
  • Thermal diffusers in the room set to their coldest, the room re-tested, and a second report issued

The result

The front of the room rose from 1,004 to 1,273 cubic metres an hour, 27% more air, and the four vents that remain open there gained between 35% and 82%. The tenant reported the improvement straight away. The report states plainly that the room is still below design until the building raises its air handling unit's output.