Offices

Office and training premises at Kallang

The client planned to reuse the old air-conditioning. Our survey found much of it dead, so we worked out unit by unit what to keep, what to replace and how to cool every new room without paying for more than it needed.

Illustration, not a drawing of the site

The brief

A training company was turning five office units of about 457 square metres into four: an open office, two classrooms, a conference room, a server room, a lounge, a pantry and a foyer. The fit-out contractor's first brief was to relocate the existing air-conditioning into the new layout.

What we found

  • Several ceiling ducted fan coil units had stopped working and had simply been left in the ceiling. One whole unit's grilles and ducted system were dead, and the foyer had no cooling at all.
  • One multi-split was beyond service. Moving it would have cost more than it had left to give.
  • A 48,000 Btu ducted unit had a choked, worn drain pump. A new pump in a coil still carrying biofilm would fail again within a short time.
  • 27 supply and return grilles served the old layout. The rooms that would actually be used needed 7.
  • A single four-room multi-split could not carry all four rooms running at once, and the foyer's walls were glass, carpentry or signage, with nowhere to hide a wall unit's pipes.

What we recommended

Keep what still had years in it, replace what did not, and size each room for the people in it rather than for the old layout. That meant two new 34,000 Btu cassettes for the open office and a classroom, keeping the existing 34,000 Btu cassette and multi-split in the second classroom and pantry, a three-room multi-split for the conference room, server room and lounge, and a separate cassette for the foyer. We advised decommissioning the failed 48,000 Btu unit rather than paying to overhaul a backup, and proposed higher-specification toilet extract fans rated to 200 Pa of duct static pressure at 38 dB, so they keep moving air through the existing runs quietly. The scope was revised four times as the layout settled, and every change was priced on paper before it was built.

The work

  • Two new 34,000 Btu ceiling cassette single-split systems for the open office and a classroom
  • A new three-room multi-split for the conference room, server room and lounge, each indoor unit matched to its room
  • A new foyer cassette, upsized to 24,000 Btu by a written variation order
  • Existing 34,000 Btu cassette and multi-split kept, one 12,000 Btu wall unit relocated to the pantry
  • Five toilet extract fans replaced with higher-specification units, complete with grilles
  • 21 redundant grilles and an error-prone mini cassette removed; condensing units of the dead ducted systems taken off the ledge
  • Chemical overhaul of the units kept from the previous layout

The result

Every room on the new plan has its own cooling, sized to how it is used, the ceiling carries only the grilles the layout needs, and the client paid for new equipment only where the old could not do the job.